Tab High geothermal plan dropped after bids double estimate; auditorium, turf and LED work planned
Summary
Capital projects update: Tab High geothermal well-field bids came in about double estimates, so district halted geothermal scope and will emphasize roof solar and scope reductions; auditorium refreshes, field turf installation, and LED conversions proceed.
York County School Division staff told the board on May 12 that several capital projects are moving forward while one planned energy project has been removed after construction bids far exceeded estimates.
Assistant Superintendent Doctor Carroll reported that Bruton High School roof repairs and final touches are nearly complete and that secondary school auditorium refreshes (curtains, seats, soundboards, stage and house lighting, flooring and ADA work) are ordered and scheduled to start June 16 with completion expected…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat