Mount Holly staff outlines downtown parking reconfiguration, paving planned for June
Summary
City staff presented a downtown parking update, noting easements recorded in 2024, council funding approval in April 2025, and a planned paving in June; the reconfigured lot will reduce the current informal layout to an estimated 15 spaces, officials said.
Get email alerts on the Parking topic
No spam. Unsubscribe anytime.
City staff presented an update on plans to repave and reconfigure a downtown Mount Holly parking lot, saying easements were recorded last year and the work is scheduled for June, weather permitting.
The update matters because the lot sits in disrepair and is used by multiple downtown businesses; staff said the reconfiguration is intended to create a more structured layout and maximize available space. "It's in pretty much total disrepair," Staff member Stephen Haney said, showing photos of the existing surface.
Haney told the council the city began discussing downtown parking at the council retreat in March 2024 and subsequently mailed letters to downtown property owners and businesses to explore options. The lot was surveyed in April 2024; easements were obtained and recorded in November 2024 at the Gaston County Register of Deeds. In April 2025 the city received a paving quote from the contractor Custom Paving and the council approved funding the same month.
The existing survey layout, Haney said, showed approximately 67 parking spots under the original arrangement. The proposed new layout "will have approximately a 15 parking spaces," Haney said, adding the change would allow a more structured arrangement to better use the site. Haney said paving is scheduled for June, dependent on weather.
The presentation was informational; council members did not take a formal vote on the item during the meeting. Council members asked whether a motion was needed; the mayor signaled the presentation was for information only. Haney answered follow-up questions from council about the plan and timeline.
Next steps identified in the presentation are completing the contractor scheduling and moving forward with the paving in June if conditions allow. The city did not provide a final construction schedule or contractor start date during the meeting.