Leonardtown awards $1.56 million contract to drill production well No. 6

3275274 · May 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commissioners awarded a contract to A.C. Schultz of Maryland Inc. to construct Production Well No. 6 near the Town Run water tower; the low bid was $1,558,160 and staff said total project costs are estimated at about $1.7 million including engineering and inspection.

The Town Commissioners voted May 12 to award the contract to construct Production Well No. 6 to A.C. Schultz of Maryland Inc., the low bidder on a publicly advertised project.

Staff reported the project was publicly advertised, with three firms attending the pre-bid meeting and one other company ultimately submitting a bid. The packet shows the total project, including engineering and inspection fees previously approved, is estimated at $1,700,660; the construction bid from A.C. Schultz came in at $1,558,160. Staff noted the well will be drilled beside the new water tower at the Meadows of Town Run 2 development.

A council member moved to award the contract at the bid amount of $1,558,160 and the motion passed on a unanimous voice vote. Council members asked whether a notice to proceed (NTP) date had been discussed; staff said they were in contact with the contractor and expected the bidder to be ready to begin work once formal award paperwork is complete.

Staff will coordinate permitting and scheduling and return details on NTP timing; construction and inspection oversight will follow standard procedures for town water infrastructure projects.