Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Pedestrian Infrastructure topic
No spam. Unsubscribe anytime.
Trustees approve $476,026 for phase 3 of ARPA sidewalk improvements linking schools and bus stops
Summary
The board awarded a $405,113 contract to Prime Construction & Excavation and approved DLZ professional services plus a 10% contingency for phase 3 of ARPA‑funded sidewalk repairs covering multiple Waterford corridors.
Get email alerts on the Pedestrian Infrastructure topic
No spam. Unsubscribe anytime.
The Waterford Township Board on April 28 approved phase 3 of its American Rescue Plan Act (ARPA) sidewalk improvement project, authorizing a $405,113.44 construction contract, a $30,400 professional services contract and a 10% contingency.
Director of Development Services Jeff Bukowski described the work as the third phase of sidewalk repairs prioritized through a PASER (Pavement Surface Evaluation and Rating) study; the phase focuses on routes that connect multiple schools and new Highland Road bus stops. Bukowski said a clerical correction in a bid calculation produced a lower contract price than earlier estimated.
A motion approved Prime Construction & Excavation as contractor for $405,113.44, retained DLZ for construction‑phase professional services at $30,400 and authorized a $40,512 contingency. The total authorized budget for phase 3 is $476,026 to be charged to the appropriate ARPA line items.
The board voted in favor on a roll call; all trustees recorded votes in favor of the project. Trustees said the pedestrian links are important for student safety and for linking neighborhoods to transit and schools. The work is scheduled to proceed under township procurement rules and with standard construction oversight.
