Cranford Zoning Board of Adjustment members on April 28 heard testimony and public comment on application ZBA24‑006, in which Cranford Park Propco LLC seeks approval to add a three‑story rear wing and associated site changes to the Cranford Hall nursing facility at 6 Lincoln Park East.
Get email alerts on the Zoning Nursing Home Expansion topic
No spam. Unsubscribe anytime.
Cranford Zoning Board of Adjustment members on April 28 (continuation scheduled from the meeting) heard testimony and public comment on application ZBA24‑006, in which Cranford Park Propco LLC seeks preliminary and final major site‑plan approval to construct a three‑story rear addition and related site work at 6 Lincoln Park East, the longstanding Cranford Hall nursing facility.
The application would add a rear three‑story wing, reconfigure parking and site circulation, and increase the facility’s licensed capacity under state rules from 100 beds to 110 beds. The applicant’s witnesses described state Department of Health and federal Centers for Medicare & Medicaid Services (CMS) processes that must be satisfied before occupancy increases. Mordecai Krauss, identified in testimony as the facility owner and licensed administrator, said he “took over the facility 2 years ago” and that the project is intended to bring the building out of annual CMS life‑safety waivers. “We are looking to get out of those life safety waivers,” Krauss said during questioning.
Why it matters: the proposal triggers multiple R‑2 zoning variances because the property is in a single‑family residential district. The board’s professionals flagged concerns about rear‑yard distance to the river, increased impervious coverage, replacement of mature trees, emergency vehicle maneuvering and stormwater control. Neighbors also pressed for details about truck deliveries, overnight garbage pickup and an interim practice of ambulances parking on the site.
Most important facts
- Application: ZBA24‑006, Cranford Park Propco LLC; location 6 Lincoln Park East; project: three‑story rear addition, interior work, two elevators and site improvements, including reconfigured parking and an underground stormwater infiltration/detention system. (Application text read into the record.)
- Variances and deviations listed in the application record include: building height (permitted 32 ft; proposed 41.6 ft), stories (2.5 allowed; 3 existing and proposed), building coverage (proposed 26.7% vs. 25% permitted), lot impervious coverage (existing 41.2%; proposed 64.1% vs. permitted 35%), and a reduced combined side yard and rear‑yard setback (existing and proposed dimensions recorded in the application). The application materials also list specific municipal ordinance subsections cited in the submission.
- Beds and rooms: Krauss testified the facility holds a 100‑bed license and is operating at about 75% occupancy. The current physical layout is 46 rooms; the applicant seeks the state‑allowed 10% increase (to 110 beds) now and described a longer‑term commercial maximum of 120 beds as unlikely and conditional on separate approvals. Architect testimony submitted to the board (and summarized in public questioning) indicated the new wing will add roughly 52 new resident rooms across two primary floors above a basement/dining area.
- State and federal oversight: Krauss and counsel repeatedly identified the Department of Health (DOH) and CMS as regulators. Krauss said the facility currently operates each year under CMS life‑safety waivers and that the proposed construction is intended, in part, to eliminate those waivers. He and counsel said the applicant has filed DOH materials related to the additional beds and that DOH approval is a precondition for increasing licensed beds.
- Parking and circulation: the applicants’ engineer testified the revised site plan would provide 55 physical parking stalls with five electric‑vehicle stalls that count as an additional credit under state guidance, for a 60‑space credit that complies with the township parking formula for a 110‑bed nursing facility. The engineer said some existing stalls are undersized and would remain in use primarily for employees; the new stalls are intended for visitors and staff. The board’s fire‑safety and engineering reviewers requested—and staff said they will supply—turnaround and reinforced paving details so fire apparatus can access the rear of the site.
- Stormwater and floodplain: the engineer described an underground infiltration/detention system under part of the new parking area, permeable pavement in some stalls, and an outlet control structure with orifices intended to reduce peak discharges (proposed reductions consistent with New Jersey DEP major‑development standards described in testimony). The engineer testified the property is not in the FEMA floodplain but acknowledged the rear of the site is adjacent to a local creek; he said the proposed system is designed to reduce peak flows off site compared with current conditions, and that operation and maintenance will be required by deeded instrument (O&M manual).
- Trees and landscaping: the applicant’s plans list removal of 50 trees. The engineer and applicant said 23 replacement trees are on the landscape plan and that remaining replacement obligations would be satisfied in accord with the township tree‑replacement formula or payments to the tree‑fund if planting on site is infeasible. An arborist’s report submitted by a neighbors’ group identified additional hazardous trees on site; township staff asked the applicant to reconcile the plan and the arborist inventory.
- Emergency services and temporary ambulance parking: neighbors told the board privately and during public comment that ambulances or other service vehicles have been parked on the property on an ongoing temporary basis. The facility owner said this was a short‑term arrangement with a vendor and agreed to remove the ambulances from the site within 30 days after the meeting, acknowledging neighbors’ reports that the vehicle storage was creating nuisance and potential safety concerns. The fire department’s review flagged the need for on‑site hydrant locations and said the applicant must demonstrate how fire apparatus will safely access the rear portions of the property; the board’s record includes the fire chief’s review letter noting unresolved items for the eastern driveway and turnarounds.
Public comments and neighborhood concerns
Neighbors asked detailed questions about: - On‑street overflow and whether the proposed parking will be sufficient (several residents said they have observed truck deliveries and ambulances using the street). - Nighttime garbage pickups and whether the contractor can be required to change pickup hours (the owner said he would address the contractor and monitor compliance). - Tree removal and replacement (residents asked for more on‑site plantings and questioned the health of trees to be removed). - Potential impacts on the creek and downstream flooding from added impervious coverage (neighbors requested clearer, peer‑reviewed stormwater calculations and stronger tree replacement). - Noise and vibration from the proposed generator location and potential effects on nearby private swimming pools and residents (the engineer said generator selection will meet local decibel limits and that noise control details will be submitted).
What the board decided or directed
- The Zoning Board left the application open for further testimony and plans and scheduled a continuation for the application (the board announced the next hearing date for the application as April 28; that continuation is part of the public record). The applicant agreed to provide additional engineering detail requested by the board and fire department (hydrant locations, driveway/turnaround geometry and reinforced paving specs, final lighting plan showing property‑line foot‑candles, trash‑enclosure details and final sanitary/stub‑connection details after municipal sewer verification).
- The applicant agreed on the record to remove ambulances currently stored on site within 30 days and to coordinate trash‑pickup hours with the neighbors and township code enforcement where warranted.
Background and next steps
The application combines bulk and design variances with site‑plan changes and requires DOH/CMS reviews before any increase in licensed beds. The board’s staff and consultants requested revised plans showing the fire‑department access details, final sanitary and water service layouts coordinated with municipal utilities, a reconciled tree‑replacement schedule based on the independent arborist report, and final lighting/landscaping details to reduce spillage to adjacent properties. The matter was continued to the board’s next hearing date for further witness testimony (engineer, architect, planner) and to allow the board’s professionals time to review revised plans.
No board vote to approve or deny was taken at this hearing. The board opened the record to more testimony and asked the applicant to submit the requested technical revisions and clarifications before the next session.
Sources and attribution
Direct quotations and paraphrased testimony are taken from the Zoning Board transcript and the witnesses who testified there: Mordecai Krauss (owner/administrator), applicant counsel (John DeMasi), civil engineer Joseph Bocce (EKA Associates) and intervening public speakers as recorded in the meeting transcript. The article does not assert any outcomes beyond what the board or speakers stated in the record.