Forest Service plans Roads End paving, culvert replacement above Boy Scout camp; brief closure expected
Summary
U.S. Forest Service District Ranger Josh Nichols told the Elko County Natural Resources Commission the agency has a contractor for parking‑lot paving at Roads End and additional funding and a contract plan to replace a failed culvert above the Boy Scout camp, which will require a temporary road closure.
Get email alerts on the Forest Service Infrastructure topic
No spam. Unsubscribe anytime.
Josh Nichols, district ranger for the U.S. Forest Service, told the Elko County Natural Resources Commission the agency has contracts lined up to pave the Roads End parking lot and to repair a failed culvert above the Boy Scout camp.
Nichols said the parking‑lot paving contract targets a start date after the week of July 4 and allows the contractor 30 days to complete the work; the Forest Service expects to keep trails open during construction and will provide limited parking at the terraces picnic area. “We’re not closing the trail,” Nichols said.
Nichols said disaster relief and other post‑storm funding will pay to replace a culvert above the Boy Scout camp that has reduced the road to one lane. He said the Forest Service is coordinating with Elko County so the county can issue the contract; the Forest Service expects to advertise the work in April with a mid‑September start target. The work will require a temporary full road closure to traffic for a period Nichols estimated “hoping for a week.” Pedestrian access will be allowed while vehicle traffic is stopped.
Nichols also gave project updates for minerals work on forest lands: the South Jarrett exploration program of work is being finalized for this year, and the Big Springs plan of operations has been submitted and likely will trigger an environmental assessment.
The district ranger said the agencies are trying to time the culvert replacement after the busy recreation season but before hunting season to minimize public disruption. No formal actions were taken during Nichols’ report.