Summary
Eagle Point Energy representatives briefed commissioners on proposed tipping-fee terms and timelines for the Orrington energy-from-waste project; county counsel is drafting indemnity language before a final contract vote.
Get email alerts on the Solid Waste Energy topic
No spam. Unsubscribe anytime.
Roy Donnelly, project manager with Eagle Point Energy, updated the commission April 15 on the Orrington energy-from-waste project and the company's proposed contract terms for municipal waste deliveries.
Donnelly said the proposed tipping fee in negotiations has been discussed in a range up to about $89 per ton with a negotiated escalator that has a 2 percent floor and a 4 percent ceiling and a 15-year term aligned with anticipated construction loan schedules. He said Eagle Point currently has supply commitments from 44 towns and a bundle of commercial haulers sufficient to underpin projected operations once financing closes.
County counsel and administration noted they requested additional indemnification and hold-harmless language because of ongoing litigation between EPIC and a prior owner/operator; counsel will produce a revised draft and the item will return to the commission for a vote once counsel and the company finalize language.
Donnelly described infrastructure and permitting progress and estimated a construction timeline of roughly 15'18 months pending financing; he said an earlier baler unit purchased to address residual on-site material remains in good condition and could help manage seasonal overflow or short-term storage needs once the permitted facility is operational.
Ending: Commissioners asked counsel to provide a draft indemnity clause and return a contract version for review; county staff said they are also comparing alternative disposal options and pricing if Eagle Point cannot finalize terms acceptable to lenders.