Fiscal court backs sewer expansion along I‑71 Exit 28 corridor and authorizes officials to seek funding
Summary
The Henry County Fiscal Court approved a resolution Feb. 13 supporting a sanitary sewer expansion along the LaGrange–Milton corridor (I‑71 Exit 28) and authorized county officials to seek state and federal funding for an estimated $9,664,660 project.
Get email alerts on the Infrastructure Sewer Expansion topic
No spam. Unsubscribe anytime.
The Henry County Fiscal Court on Feb. 13 approved a resolution expressing the county’s full support for a sanitary sewer expansion along the LaGrange–Milton corridor (I‑71 Exit 28) and authorized county officials, including the county judge executive, to seek state and federal funding for the project.
The resolution, read into the record at the meeting, said the corridor anticipates rapid commercial and residential development and that many properties lack sanitary sewer service or rely on failing on‑site systems, which hinders economic growth. The resolution recounted a 2013 submission by the county and the LaGrange Utilities Commission to the Kentucky Infrastructure Authority for a proposed extension and cited an estimated project cost of $9,664,660.
Court members noted Henry County has applied for a loan from the Kentucky Clean Water State Revolving Fund but had not yet received funding. The court approved the resolution and the judge executive said he would present the signed resolution to state and federal representatives as part of outreach for grant and loan support.
The resolution directs county officials to pursue necessary funding at local, state and federal levels and to provide personnel and facilities as available to support project assessment and completion. The transcript records a motion associated with the resolution and a member identified as Kevin noted the motion; the court chair said the resolution would be signed. The transcript does not include a roll‑call vote tally.
County staff said engineering work and earlier planning documents were already in place and that further coordination with the utilities commission and development district would continue as the county seeks grant and loan approvals.