Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Broadband Access topic

No spam. Unsubscribe anytime.

Highline Communications asks Liberty County to expedite permits for grant-funded broadband build

3110872 · April 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Representatives of Highline Communications asked the Commissioners Court during public comment to consider an open permit policy to speed placement of fiber under a federal/state grant that requires completion within 18 months.

At the start of the April 8 meeting, representatives of Highline Communications addressed the Liberty County Commissioners Court during public comment to request county assistance in accelerating permitting and coordination for a grant-funded fiber build aimed at serving underserved and unserved areas.

Glenn Sherwood, representing Highline Communications, said the company received grant money subject to an 18-month construction deadline. “We only have 18 months to do this job,” Sherwood said. He asked the court to consider an open permit or expedited coordination with county utility and right-of-way staff so Highline can meet the grant timetable.

Sherwood described the grant as intended to fill gaps in fiber service and said Highline will use grant funds for the targeted areas while committing to cover additional buildout costs beyond the grant-funded sections. He said Highline already serves multiple states and has established local ties in areas including River Ranch, Dayton, Harding and Kennefick subdivisions.

Court members did not take questions from the bench during public comment; the judge directed Sherwood to follow up with county staff, advising him to contact Didi or Joanie in the judge’s office to coordinate next steps.

Sherwood said Highline had maps of proposed build areas and sought either scheduled meetings with relevant county departments or other assistance to move permitting and placement forward within the grant’s time limits.