Dunn County road staff outline permitting, cultural-site constraints and upcoming bids

3110460 · March 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Road Department staff updated commissioners on multiple road design and permitting efforts, described recurring right‑of‑way holdouts and cultural‑resource constraints, and announced bid openings and recommended awards for several pavement projects.

Road Department staff delivered a multi‑project update to the Dunn County Board of Commissioners, reporting progress on design, permitting and expected construction this year while flagging recurring right‑of‑way and cultural‑resource constraints.

The department said 80 Sixth Avenue remains under review after a developer requested extensive testing that would extend beyond existing rights‑of‑way; staff said some landowners refuse permission for off‑right‑of‑way testing. Carl, speaking for the Road Department, said the county is trying to avoid going beyond proposed grading limits and will seek mitigation bank credits for wetland impacts when necessary.

Why it matters: several of the county’s 2024–2026 road projects face delays or added cost because cultural resources and wetland avoidance have required plan revisions and extra permitting, and because unresolved right‑of‑way agreements can stall construction despite finished plans.

Key project notes provided by staff: - 80 Sixth Avenue: staff are evaluating Chippewa’s recommendation and whether testing outside current right‑of‑way is necessary; landowner resistance to expanded testing remains unresolved. - 100th Avenue NW / Second St NW: a civil project with bids received; staff will recommend awards after tabulation. - Several 2025 projects (Third Street NW; Seventh Street SW; Twelfth Street) are in formal design; cultural resource reports have required plan changes to minimize wetland impacts.

Staff said they plan on environmental and cultural surveys for the 2026 projects and expect design work to begin early this summer. Commissioners pressed staff to meet on site for projects where right‑of‑way or landowner holdouts could make continued design work futile. Commissioner Heizer and another commissioner said they plan to visit problem sites before deciding whether to suspend work if rights cannot be secured.

Road staff and county engineers also announced bid openings and tabulations. For one project (project 2604/Eleventh Avenue and 20 Second Street) Bronco Brothers submitted the verified low bid and staff recommended award; for the 100th Ave NW / Second St NW civil project Bronco Brothers again submitted the low verified bid and staff recommended award. Commissioners moved to award both projects to Bronco Brothers; votes were recorded by roll call and the motions carried.

Staff urged commissioners to approve notices to proceed for contracts where agreements, bonding and insurance are in order, and to consider site meetings with property owners early in design to reduce holdouts. The department also recommended limiting wetland mitigation purchases by minimizing impacts in ditches where feasible.

The update closed with staff noting upcoming construction schedules, a recommendation to proceed with concrete paving for one truck‑stop access project after lifecycle analysis, and a reminder that some projects will remain contingent on federal Corps of Engineers responses for 404 permits.

Ending: Commissioners did not change county policy in the presentation; they asked staff to pursue site visits, continue to secure permits and easements, and bring final bid award documents and contract packages back for signature at the next meeting.