Commissioners discuss phasing and contracting options for North Annex repairs; $88,000 previously approved awaiting contract signature
Summary
County officials discussed options to phase North Annex renovations — elevator, building squaring, HVAC — and whether to hire one general contractor or contract work in pieces. The board noted $88,000 in prior approval is not yet under contract and further review is scheduled at a meeting with a contractor next Monday.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
County leaders discussed plans March 27 to proceed with phased repairs at the North Annex, including an elevator installation and other second-floor work, and debated whether to bundle the work under a single general contractor or to break it into multiple contracts.
A county representative said they met with a contractor who indicated the work could be separated by scope (elevator, building “squaring,” HVAC). The representative said the contractor was confident the county could piece the project out so elevator work could start on the second floor while other elements follow, and noted HVAC is already in place and might not need to be included in the immediate procurement.
Commissioners raised a concern that phasing could increase costs through repeated mobilizations by different contractors, asking whether it would be cheaper to do the work in one general-contract package. The representative said the contractor indicated the county could serve as general contractor if it chose, or instead proceed with a formal bid and select a general contractor through the bidding process.
Board members noted the project previously received an $88,000 approval but that the county has not signed a contract for that work; staff said contract documents were to be refined and expected at the Monday meeting with the contractor. The board scheduled a follow-up meeting with Ryan and contractor John Miller for 9:00 a.m. on Monday to review how the project can be executed and whether work will be bid as a single contract or pieced out.
No final procurement decision was made at the March 27 meeting; staff will return with refined contract documents and clarification of bonding and scheduling before the board signs a contract.