Airport director warns of expected extras as Saratoga County terminal nears substantial completion
Summary
Airport Director Chad told the committee on March 4 that exterior work on the Saratoga County Airport hangar and terminal is complete and that interior coordination among trades is prompting expected additional costs on the $36 million project.
Airport Director Chad told the Airborne Improvement Committee on March 4 that the terminal and hangar exterior work at Saratoga County Airport is complete and that contractors have moved inside, prompting expected additional costs as trades coordinate interior fit‑out.
Chad said the project was fast‑tracked to meet grant requirements and estimated that 5–10% of large vertical projects’ budgets is a reasonable contingency for additional costs. He called the project a…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat