US Solar outlines 7-MW project near Lennox, cites $1.4M grid upgrades and local tax revenue

3068850 · April 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

US Solar presented plans for a 7-megawatt, 43-acre solar facility northwest of Lennox, describing setbacks, screening, maintenance, decommissioning requirements and an estimated $1,400,000 of distribution upgrades paid by the developer; no formal council action was taken.

US Solar project developer Luke told the Lennox City Council that the company is proposing a 7-megawatt solar facility on about 43 acres northwest of the city that would interconnect to the local substation roughly 1.7 miles away.

Luke said the project would include tracking modules, about 6–9 feet high at times, 6–7-foot page-wire fencing, planned tree screening and pollinator-friendly ground cover. He said US Solar expects to fund roughly $1,400,000 in distribution-line upgrades between the substation and the site and estimated about 25 temporary construction jobs during build-out and quarterly site visits thereafter.

Why it matters: The proposal is a private development on land outside the city boundary but inside the council’s planning jurisdiction; the council normally offers a position to the county planning commission on projects in the county. If built, the project would generate local property/production tax revenue divided among the Lennox school district, Lincoln County and the township, supply low-maintenance electricity into the distribution system and require county zoning approvals and a utility interconnection agreement before construction.

Details and questions from council and staff: Luke described setbacks and screening plans — roughly 140 feet on the east/front yard, more than 200 feet on the north, smaller setbacks on the south and rear setbacks of about 10–20 feet — and said the project would have no lighting, only remote-monitored cameras, and a small bottom gap in fencing to allow small animals through. He said the company proposes planting an initial row of trees and pollinator habitat inside the fence line and would work with neighbors on additional screening. On stormwater, Luke said US Solar proposed a south-side basin, repair or replacement of an undersized northeastern culvert and maintenance of an eastern ditch to reduce runoff compared with row crops.

On construction and operations, Luke said "the loud part of construction is that driving of the steel I beams" but that the overall build time would be about 10 weeks plus commissioning. He told the council, "You should not be able to hear a solar facility if it's operating correctly from outside the fence area," and that the company has not proposed battery storage for this site.

Regulatory pathway and outstanding steps: Luke said Lincoln County currently lacks a solar-energy-specific ordinance and that his company would expect to apply for a change of zone from agricultural to a planned-development district (PDD) with conditions set by the county. He said an interconnection agreement and a commercial arrangement with the utility (described as Xcel Energy during the presentation) would be required; the interconnection study produced the $1,400,000 upgrade estimate. Luke also said decommissioning terms would be included in the site lease and in the county permit application and that many jurisdictions require a financial surety (bond, letter of credit or cash) to guarantee removal at project end of life.

What remains unresolved: Luke said neighborhood questions—primarily stormwater management and visual screening—are still being addressed in conversations with the nearest landowners and the township. He said US Solar has not yet submitted a formal application to Lincoln County and estimated a submission window of about three to six months if the developer proceeds.

No council action: The council received the presentation for information only and did not vote or take a formal position during the meeting.

Ending: Luke left contact information for the city and indicated the company would continue outreach with immediate neighbors, the township and county planning staff if the project advances.