Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Subdivision Preliminary Plan topic
No spam. Unsubscribe anytime.
Council approves preliminary plan for Lot 7A in Stakes Addition amid drainage concerns
Summary
The Lennox council approved a preliminary subdivision plan adding a cul-de-sac and three lots at the end of Windsong, with staff and developer addressing drainage and detention concerns and exploring use of the school district’s detention facility as a solution.
Get email alerts on the Subdivision Preliminary Plan topic
No spam. Unsubscribe anytime.
The Lennox City Council approved a preliminary plan for Lot 7A in the Stakes Addition, a small subdivision extension that would add a cul-de-sac and three buildable lots at the end of Windsong.
City planning staff described the process: the preliminary plan is the first of several steps required under local subdivision regulations. If the council approves the preliminary plan, the developer will perform more detailed engineering — particularly drainage and detention analysis — before final platting and construction. Planning staff noted the city's regulations typically require dedication of streets, water and sewer mains to the city and either on-site open space or a payment into the park system; because the site is small and adjacent to an existing park, staff recommended a fee-in-lieu for park dedication.
A primary point of discussion was drainage. The site has areas of existing ponding; staff said the developer is exploring options including cooperating with the school district to expand the district detention facility to the north, creating a low-lying storage area on adjacent land, or using a small detention area on Lot 3 — though staff said Lot 3 detention is likely infeasible. Staff stressed that any use of property outside the development will require the developer to secure permission from those landowners.
Council members also raised concerns about construction traffic and potential wear to Windsong, driveway approaches for the new lots, and whether the existing access to Elm for Lot 3 should be closed. Staff suggested pre- and post-construction video documentation of the roadway condition and said the developer will be required to secure required easements and maintenance agreements if using neighboring detention facilities.
The motion to approve the preliminary plan passed by voice vote; the clerk recorded a voice approval and the transcript records the motion, second and verbal adoption. Staff will continue to review engineering submittals, especially drainage calculations and proposed detention solutions, during the next design phase.

