Sloane Elementary construction reaches roughly 25% complete; first slab pour planned for May
Summary
Construction managers reported March–April progress on the Sloane Elementary project at the April 7 board meeting: precast erection is complete, structural steel and roofing are underway, utilities are nearly installed and the project is roughly 25% complete with the first slab pour scheduled for early May.
Project representatives gave the board a monthly update on the Sloane Elementary construction at the April 7 meeting, reporting that site work resumed after winter and that the project was gaining momentum.
Representatives from JD Dunn said precast components had been erected and that structural steel, roof work on the gymnasium and north classroom wing, canopy…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat