City staff outline preliminary timeline for DPS bond projects; ladder truck purchase to follow closing
Summary
City staff presented a preliminary timeline for a new DPS building, South Side remodel, downtown fire-station rehab and a ladder truck purchase; staff emphasized the timeline is contingent on dependencies including staffing and closing funds.
City staff presented a preliminary schedule for several public-safety projects, saying drawings and bidding will take months and some work depends on staffing and the timing of available funds.
Mr. Gilbert, a city staff presenter, told the Fate City Council that, once an architect is under contract, it will take about six to eight months to produce drawings. He said construction of a new DPS building is estimated at 12 to 14 months, a South Side remodel about eight months, downtown fire-station…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat