At the meeting the commission approved an agreement with Rio Grande Pacific Corporation not to exceed $100,000 for rail‑review work, issued a task order to Lanier and Associates for HVAC design, and increased a contract for an economic‑impact analysis; votes were typically unanimous or near‑unanimous on those items.
Get email alerts on the Votes Summary topic
No spam. Unsubscribe anytime.
The Plaquemines Port Harbor and Terminal District commission voted on several contracts and ordinances during the meeting.
Key votes at a glance
- Agreement with Rio Grande Pacific Corporation to review rail extension design: commissioner Schultz introduced the resolution and it passed 9–0. Port staff described the contract as “not to exceed $100,000” and said the amount will be funded from the rail extension budget.
- Task order No. 13 to Lanier and Associates for engineering services (detailed HVAC design for the Administration Building renovation): introduced by commissioner Schultz and passed 9–0.
- Ordinance increasing the contract amount for Dr. Lawrence Scott (economic impact analysis): introduced by commissioner Schultz; after discussion the ordinance passed 9–0. The executive director described expanding the study to include long‑range forecasts to support grants and public messaging.
- Several other routine items and procurements passed unanimously or by strong margins; approval of the March 13, 2025 minutes passed 8–1. A motion to adjourn later passed 8–1 with a recorded no vote from Mr. Edwards.
Votes and procedure notes
Port staff stated publicly that the Rio Grande agreement is within executive authority limits but was presented to the commission for transparency; the port described the funding source as the rail extension line in the budget. For the Lanier task order, commissioners discussed ongoing complaints about temperature control in port buildings before approving the HVAC design work. For the economic study, staff said the original study estimate had been $100,000 and that the expanded scope will cover longer forecast periods and large prospective projects such as Venture Global.
No later binding procurement awards or final contract executions were recorded in the open meeting minutes; staff said some actions are within executive authority and will proceed through contracting as authorized.