The committee approved a block of late contract resolutions (Nos. 197–200) advancing construction on a Government Operations Center. The block, amended and adopted 7–0, included a $9,355,000 contract with Rock Construction Corporation described as the general-contractor agreement; county staff said industry-standard contract templates were used.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Ulster County Legislature’s committee on April 15 approved a block of late contract resolutions (Nos. 197–200) related to construction work on the County’s Government Operations Center. The block—amended as presented—was adopted unanimously, 7–0.
Committee staff said the resolutions advance construction and each resolution represents a separate contract needed for the project. One resolution, Res. 197, approves execution of a contract in the amount of $9,355,000 between the county and Rock Construction Corporation; presenters described Rock Construction as the project’s general contractor. Staff explained the use of a more detailed contract template (referred to in the meeting as an “NIA contract”), which they said is common in the industry because it contains more comprehensive materials than the county’s standard templates.
The Department of Public Works and county project staff attended the meeting to answer questions. Committee members conducted a block vote on Resolutions 197, 198, 199 and 200, moved to amend as presented, and then adopted the block. The roll-call read in the transcript recorded a unanimous “yes” from members present, and the clerk announced the resolutions were adopted, 7 to 0.
The committee did not discuss specific funding sources or detailed payment schedules for each contract in the excerpted discussion; staff indicated the contracts are part of the construction procurement and are standard contracting practice for the project. The resolutions were filed as late contract resolutions and were considered together to accommodate the project schedule.
The committee’s approval authorizes execution of the listed contracts; staff and DPW representatives indicated they are available to answer follow-up questions and that the contracts reflect industry-standard provisions.