Drainage Committee approves series of culvert, outfall and canal projects; tables engineer contract question
Summary
Assumption Parish Drainage Committee approved multiple small drainage and culvert projects, allocated funds for piping and equipment delivery, and directed staff to obtain engineering plans and quotes for larger projects.
Get email alerts on the Drainage Projects topic
No spam. Unsubscribe anytime.
The Assumption Parish Drainage Committee approved a slate of small-to-medium drainage projects on Thursday, authorizing culvert replacements, outfall cleaning, and material purchases while tabling a question about an engineering contract.
Committee action and why it matters: The approvals cover localized repairs — collapsed culverts, outfall cleaning, and purchase of piping for a pump station — that maintenance staff said are causing recurring flooding or safety issues. Committee members said some jobs are urgent and can be done with in-house crews or by contractors once quotes are obtained; others require stamped engineering plans.
Key approvals (summary): The committee voted to approve multiple projects including: - Culvert replacement and drainage repairs at 3700 Highway 1 ($4,850) — motion by Mr. Blanchard, second by Mr. Pearl; approved. - Culvert replacement at 115 French Lane ($790) — motion by Mr. Brophy, second by Mr. Patterall; approved. - Culvert replacement on Little Texas Road ($1,500) — motion by Mr. Bridal, second by Mr. Carter; approved. - Clean out outfall from Georgia Street to Georgia Plantation and Supreme (about $1,000) — motion by Mr. Blanchard, second by Mr. Bridal; approved. - Sweep/repair of a large outfall ditch (Economy 8 of Old Ditch) estimated $5,000 — motion by Mr. Brookes, second by Mr. Carter; approved. - Delivery cost for excavator on Project 93223 ($700) — motion by Mr. Carter, second by Mr. McTernan; approved. - Allocation of GO MESA funds to purchase 24-inch discharge piping for the Paul Street pump station (estimated $35,000) — committee directed staff to obtain three quotes and to use the parish procurement/bid process; approved.
Items requiring further engineering: Committee members emphasized that some outfalls and collapsed large-diameter outfalls require stamped engineer plans and trench safeguards (trench boxes) because of depth and proximity to highways. An item authorizing up to $32,025 for a principal engineering contract for Project 93229 (Ward 2 outfall) was discussed and tabled pending presentation of photos and additional details.
Process directions: The committee instructed staff to: - Request stamped engineer plans when work exceeds simple clearing or when structural replacement is needed. - Obtain three vendor quotes before purchasing large piping or specialized materials. - Log and track procurement of equipment and track project costs to avoid overruns.
Votes at a glance: All listed project motions were approved by voice vote; the transcript shows routine “Aye” responses and no recorded roll-call tallies.
Ending: The committee advanced multiple maintenance projects to address acute drainage failures and directed staff to secure engineering plans and vendor quotes for larger, higher-risk work.