Frostburg gives monthly update on CSO projects; phase near Mountain Ridge to continue through summer
Summary
Public works provided a monthly combined sewer overflow project update: phase 10a near Mountain Ridge High School resumed after winter, work is expected through late summer/early fall, and design is complete for later phases that will be bid in May.
City of Frostburg public works staff on April 15 provided the monthly public hearing update required for combined sewer overflow (CSO) projects, outlining five active phases and timelines for construction and bidding.
Public Works Director Hayden Lindsey said phase 10a — work below Mountain Ridge High School — has restarted after a winter shutdown and is expected to be substantially complete by late summer to early fall. “We anticipate that project being over, in the early fall to late summer time frame about September,” Lindsey told…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat