Norwalk Fire: Station 1 floor drawings delayed; Station 3 refurbishment complete; overhead doors ordered

2988181 · January 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Assistant Chief Conti updated commissioners on multiple station projects: Station 1 apparatus-floor drawings are still being finalized, Station 3 floor work is complete with a planned return in a few weeks, station 4 renovation final cost analysis submitted, and overhead doors for all stations have been measured and ordered.

Assistant Chief Conti told the Norwalk Board of Fire Commissioners that construction and maintenance work across multiple stations is progressing but staged to avoid rework.

Conti said Station 1 apparatus-floor drawings remain under final review; the department hopes to submit cost figures next month and begin construction thereafter. Station 3’s apparatus floor work — including repainting, sealing and concrete curing — is complete; crews are delaying moving firefighters back in for a few weeks while final punch-list items are finished and photos will be provided to the board next month.

Conti said the final cost analysis for Station 4’s building renovation has been completed and was included in the department’s capital funding materials. He praised a vendor named Guardian for continued repairs and support during renovation work.

On overhead doors, Conti said measurements were taken for all commercial station doors; the department intends to order all doors at once and store extras at Station 6’s apparatus maintenance until Station 1’s floor work is complete. Delivery for commercial doors is expected to take several months.

Why it matters: coordinated timing for floors and doors is intended to avoid installing new doors before floor replacement, and the board will receive photos and cost information as projects proceed.

Speakers: Assistant Chief Conti; Chief Gatto (submitted capital funding).