Westland outlines 2025 public-works calendar; flags ODOT Highway 43 timing and operations-facility wetlands

2984113 · February 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works Director Eric Laius outlined Westland’s draft 2025 construction calendar, including water-line replacements, the summer road program, Ninth Street sidewalk design, corridor-safety studies and initial design work on the city operations facility.

Public Works Director Eric Laius presented the city’s draft 2025 project calendar, noting planned water-line replacements, a summer road program, sidewalk and corridor safety work, safe-routes-to-school coordination and early work on the city’s operations facility. The council discussed communication with ODOT about planned Highway 43 work.

The calendar items and near-term actions:

- Water-line replacement: Annual program to replace substandard cast-iron and asbestos-cement mains with ductile iron; property owners received door hangers and staff described standard on-site notification procedures for construction.

- Summer road program: Grind-and-overlay plus cement-treated base where subgrade is poor; work is expected in the north (Upper Mid Hill/Hidden Springs and Rosemont areas) pending bids and coordination with the water-line schedule.

- Ninth Street sidewalk: Design consultant engaged to produce plans for a gap in pedestrian facilities; site constraints include wetlands and retaining-wall needs.

- Corridor and pedestrian-safety studies: Consultants are reprioritizing the city’s 2016 pedestrian list in coordination with the Transportation Advisory Board; specific corridor work includes Nineteenth Street/Ostman, Cornwall/Oxford intersections and Sunset Primary area crosswalk/warrants analysis.

- Safe Routes to School and other targeted pedestrian projects: Cedar Oak, Bittner/Long and other priorities are under study with the school district and neighborhood input.

- Operations facility: Geotechnical borings and a wetland delineation were underway. Staff reported a wetland area on the site that will affect the building footprint and design; staff intend to seek concurrence from state lands and remove woody debris once permits are in place.

Council concerns and requests: Several councilors asked the city to press ODOT for earlier and clearer communication about Highway 43 work after residents reported short notice for recent projects. Councilors also requested a joint meeting with the Transportation Advisory Board to align funding priorities and consider potential grant opportunities. Staff agreed to reach out to ODOT and to schedule a TAB/council session on pedestrian-safety funding and prioritization.

Ending: Staff will improve early neighborhood outreach (door hangers, project web pages and direct contacts) and bring a proposed funding and prioritization plan to a joint council/TAB work session ahead of the FY2026 budget.