County to consider awarding Taxiway Alpha bid to Pyramid; fuel farm bids rejected and staff exploring options

2980439 · March 26, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Airport staff told the board the low bid for the Taxiway Alpha project came in under the engineer's estimate and will be on the county commissioners' agenda for award; bids for the fuel farm came in high and staff will recommend rejecting them and exploring options including expanding material quantities under the taxiway contract.

Airport staff told the Chaffee County Airport Board that bids for two capital projects arrived with different outcomes: a favorable low bid on the Taxiway Alpha project and less favorable bids for the planned fuel farm.

Staff said the Taxiway Alpha low bid was slightly under the engineer’s estimate and that the county commissioners will consider awarding the taxiway construction to Pyramid at their upcoming meeting. Staff plans to negotiate with Pyramid and Pro Electric on potential contract adjustments if commissioners approve awarding the taxiway contract.

By contrast, staff said bids for the fuel farm project were not favorable; the airport will ask the county commissioners to reject or cancel those bids. Staff described options to move forward that include increasing quantities of asphalt and concrete work under the taxiway contract to cover grading and site preparation for the fuel farm so the airport can proceed while procurement options for the fuel tanks are re-evaluated.

Supply-chain and pricing issues were raised in the discussion. Staff reported that tariffs and rising material costs—specifically for stainless steel used in above-ground piping—have contributed to volatile pricing. One contractor told staff a stainless-steel piping estimate would only be valid for 24 hours, underscoring price uncertainty.

Airport staff said they will request direction from the county commissioners at the Tuesday meeting and then meet with the low bidder and subcontractors to determine next steps. No final award or contract amendment was decided at the airport board meeting.