County outlines road-resurfacing procurement timeline; expects multi-million-dollar program and competitive bidding
Summary
County staff told commissioners that road-resurfacing bids are due March 27 and that the county expects to recommend a vendor April 1 and award contracts around April 15. Staff said state law requires competitive procurement for road work and estimated the program could cost about $5 million.
Get email alerts on the Transportation And Roads topic
No spam. Unsubscribe anytime.
Baldwin County staff briefed the Board of Commissioners on the road-resurfacing schedule and procurement requirements, saying bids are due March 27, the county expects to recommend a vendor on April 1 and anticipates awarding the contract around April 15.
Staff emphasized Georgia law requires competitive procurement for road construction work and noted a countywide resurfacing program could total about $5 million. The board was told the county cannot shortcut the statutory procurement steps and that actual resurfacing schedules are determined by contractors once contracts are awarded.
A commissioner asked how many miles would be resurfaced; staff estimated the program could cover more than 15 miles but said the exact schedule depends on the awarded contractor. Staff also said that state law requires advertising for four weeks prior to award.
Why it matters: road-resurfacing contracts and schedules affect travel safety, local budgets and the timing of construction in neighborhoods across the county.
Staff also noted an ongoing bid process for the splash pad at Coopers Park and other capital projects; these items were presented as part of the manager's report and procurement calendar rather than discrete votes.