Council committee briefing outlines $40 million Postpoint emissions control project and timeline
Summary
Council's Public Works committee received a briefing on air‑emission control upgrades at the Postpoint wastewater treatment plant. Staff estimated approximately $40 million in costs and a four‑year timeline for design, permitting and construction to meet forthcoming air regulations for incinerators.
Get email alerts on the Wastewater Infrastructure topic
No spam. Unsubscribe anytime.
Bellingham city staff briefed the Public Works and Natural Resources Committee March 24 on a major emissions control project at the city's Postpoint wastewater treatment plant. The briefing described options for upgrading sewage sludge incinerators and installing air‑pollution control equipment to meet anticipated, more stringent regulatory requirements.
Staff gave a preliminary cost and schedule estimate: about $40 million and roughly four years to complete design, permitting and construction. Mike Olinger, interim public works co‑director, and consultant Casey Gish (Brown & Caldwell) presented technical findings and site considerations. Committee members were briefed on the regulatory context, the city’s prior decision to abandon biodigestion planning in 2022 because of PFAS concerns, and the near‑term need to maintain incinerator operations in compliance with air rules.
Why it matters: The project affects the city's wastewater solids handling strategy and carries significant capital cost and permitting complexity. Staff told the committee the city must pursue the emissions control project irrespective of longer‑term solids management decisions, while continuing to monitor emerging technologies.
What staff said: The briefing outlined major design and permitting steps, options under review, and site constraints at Postpoint. Preliminary material estimated the work would include new air‑pollution control systems compatible with the existing incinerators and would trigger multi‑year procurement and construction work.
Next steps: Staff indicated the city expects to return next year with materials for possible contract awards. Committee members and staff encouraged interested members of the public to watch the recorded presentation for technical detail.
Taper: Committee discussion was informational; no action was taken. Staff will return with project proposals and recommended procurement steps as design and permitting work progresses.