Norwalk fire chiefs warn multi‑year delays for new engines, rescue truck
Summary
Norwalk Fire Department leaders told the Board of Fire Commissioners that two engines and a heavy rescue on order now have delivery dates in 2026 and 2027, and that industry‑wide supply and staffing issues are driving longer build times.
Get email alerts on the Apparatus Delivery topic
No spam. Unsubscribe anytime.
Norwalk fire leaders told the Board of Fire Commissioners on a February afternoon that delivery schedules for new frontline apparatus have slipped several years, leaving the department to continue relying on older vehicles.
Assistant Chief Christopher McCabe, speaking for operations, said two replacement engines are now scheduled for delivery in August 2026 and the department’s heavy rescue truck is slated for September 2027. "Those engines and the rescue should have come online in 2022 and in 2023," McCabe said. "We've not seen that (improvement) — it's industry wide."
The department said the extended timelines stem from a combination of factors: lingering supply‑chain delays from the COVID period, a backlog of manufacturer orders and workforce shortages at manufacturers after retirements. McCabe said those factors together account for roughly four‑year waits for some apparatus.
Chief Gatto and McCabe told commissioners the longer lead times increase strain on the department’s mechanics division and raise the cost and operational risk of keeping older units in frontline service. "Our mechanics continue to do a good job, keeping us on the road, and it's something that we're continuing to watch in the industry," McCabe said.
Commissioners acknowledged the operational and budgetary pressure but did not take formal action at the meeting. The department said it will continue to monitor manufacturer schedules and report updates to the commission.
Ending: The department’s published replacement schedule will remain in flux until manufacturers shorten lead times or alternative procurement options are found; the fire department plans to update the commission as delivery dates change.