Committee forwards LIDAR/geo‑spatial enhancement proposal to full county board after questions about hosting and fees

2978086 · April 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The committee discussed a proposed contract to enhance and host county LIDAR/geospatial data, heard the estimated total project cost and sources of grant funding, and voted to send the item to the full county board with additional information requested from staff.

The Finance Standing Committee discussed April 8 a proposal to enhance, host and make the county's 2021 LIDAR and orthophoto data more usable for county departments and the public. Staff said the contract work would consolidate disparate data tiles, add enhancements and provide an online platform so county users — including emergency management, the sheriff's office and planning and zoning — can access the information in one place.

Staff told the committee the total cost for the LIDAR enhancement project is about $112,450. Funding sources cited at the meeting included the NG911 grant, the 2024 land information grant and retained fees derived from recording document fees. Staff said 2024 grant funds must be spent by the end of 2025. Committee members sought clarification on hosting arrangements and any ongoing annual hosting fee; staff said hosting and any annual fee were not clear from the materials provided at the meeting and promised to return with contract language and hosting cost details.

Committee members also discussed public access. Staff said the county could make the hosted LIDAR data publicly accessible; some counties charge for access while others do not. Members noted the county owns the underlying data and could opt to host itself if the county later chose not to continue a hosting contract.

A committee member moved and the committee approved forwarding the agreement and staff materials to the full county board for final action, with the understanding Kathy (land information staff) would provide additional information on hosting terms and any recurring fees.

Ending: The committee advanced the LIDAR/geospatial contract to the full county board, asking staff to supply contract language and clarify hosting arrangements and any ongoing costs before the full‑board vote.