Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Transmission Pipeline topic

No spam. Unsubscribe anytime.

West Transmission pipeline progresses; Dean Sullivan closure expected for days, contractor reports tunneling setback from flooding

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City engineer reported steady pipe installation on both segments of the West Transmission project, trenching methods, and a bore pit flooded during recent storms that damaged tunnel-boring machine electronics; planned short-term closures including Dean Sullivan are expected to last a few days.

Corey Grama, utilities engineer, updated the Water & Sewer Committee on April 8 on the West Transmission pipeline project, reporting steady progress on both construction segments and describing methods crews are using to lay and protect 50-foot pipe sections.

Grama described use of large trench boxes on straight alignments and smaller trench boxes in topographic or curving areas. He said more than 60% of the pipe is on-site and roughly 3,000 feet of segment 1 and 2,400 feet of segment 2 have been installed (each representing about 8% of its alignment). He noted deliveries, tracer-wire installation, and corrosion-coating work being completed before pipe is lowered into trenches.

On public impacts, Grama said crews will close Dean Sullivan for a multi-day full closure (24 hours per day) when they cross that road; he estimated the contractor requested a week but that work is likely to take three to four days unless unforeseen events occur. Committee member Theresa Turk asked to be notified in writing; Grama agreed to email a detailed schedule the next morning.

Grama warned heavy rains caused groundwater to overtop a bore pit for the Clear Creek tunnel south of Reed Valley Road. Pumps could not keep pace with groundwater and floodwater; the tunnel-boring machine sustained electronic damage. “They don't seem worried about it,” Grama said; contractor staff expect about a week to obtain parts and return the bore to service.

He also described a forthcoming specialty tapping operation to connect the new main to an existing 36-inch prestressed concrete cylinder pipe; the contractor Range Line (from Texas) will perform that tap because the material requires specialized expertise. Grama said that connection will create a temporary 36x24-inch outlet that will later be expanded when the Highway 112 relocation ties multiple stubs into a 48-inch line.

Why it matters: the project advances a large transmission main intended to increase system capacity, but it involves localized traffic impacts, specialized construction methods, and a schedule sensitive to weather and tunneling risks.

Grama said he will provide council members with closure timing and other public-facing details in writing prior to the Dean Sullivan closure.