Olive Branch approves $4.5 million Kraft Road widening with DeSoto County cost share

2967055 · April 1, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a joint city-county agreement to widen Kraft Road, with DeSoto County contributing $2 million and the city responsible for management and the remainder of the estimated $4.5 million project.

The Olive Branch Board of Aldermen approved a partnership with DeSoto County on a Kraft Road widening project, voting to accept the county's offer to contribute $2 million toward an estimated $4.5 million build.

Under the agreement, the city will manage the project, advertise bids and pay the remaining estimated $2.5 million; the county's $2 million contribution covers part of the work inside the city's jurisdiction. The project would extend five-lane sections of Kraft Road northward to just south of College Road to improve school-area traffic flow and increase capacity along a growing north–south corridor.

City staff described the measure as a strategic step toward extending Kraft Road five lanes from MS-302 toward I‑269 over time. The board approved the agreement after a motion by Alderman Wallace and a second by Alderman Collins. The motion carried by voice vote; the transcript does not record a roll-call tally of individual named votes.

The city will be responsible for contract overruns and project management. Bids will be issued under the city's procurement process; the timeline for advertisement and construction was not specified in the discussion recorded on the transcript.