District reports progress on multiple construction projects; board schedules extra April meeting to accelerate hiring
Summary
The district’s construction lead reported that Stage 1 of a new building is in use, Phase 2 work is underway with a May 30 targeted completion for some connectors, and athletics and site projects are progressing. The board agreed to add an April 24 business meeting to speed hiring ahead of summer.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
Morgan County Schools staff gave a multipart construction and facilities update covering classroom buildings, athletic facilities and site work, and the board agreed to add an extra business meeting in April to accelerate hiring.
At the start of his report, Mr. Elliott said the district moved into the Stage 1 building in December and that classrooms in that space are already being used. He described Phase 2 demolition and bathroom remodels and said the connector between the U Building and the existing building is scheduled for completion May 30, and that weekly contractor meetings are being held to track progress. Elliott said one project segment is roughly $300,000 under budget and that the district is retaining roughly a million dollars in retainage while contractors finish work.
Elliott provided photographic progress descriptions: interior classrooms, library circulation desk installation, cafeteria overhead inspections, science lab finishes, and a gym where crews will start laying wood floor. He said the district is working on baseball and softball facilities (dugouts and concession stands) with a target to complete Phase 1 by May and turf/finishing work following in Phase 2; he again noted a reliance on dry weather for field work.
On Danville High School work, Elliott said Waya Construction has a contract worth about $1,800,000 and the contractor aims to finish by August; the work includes a new concession/bathroom structure, a press box and new bleachers that will be made handicapped accessible on the west side. He said project footers and gravel work were underway and that crews planned to pour the slab the week following the report.
Elliott also described improvements at Lacey Springs—adding a clearer entrance and replacing long‑delayed windows—and said the community had been appreciative. He announced an upcoming Partners in Education new‑teachers breakfast set for July 29 at 7:30 a.m. at the Cook's Museum.
Board members and staff agreed to add another business meeting on April 24 at 4:30 p.m. to get ahead on hiring and personnel items so the district can post openings earlier and avoid crowding meetings in June. That scheduling decision was recorded in the meeting exchange.
No project closeouts or final construction acceptances were recorded in the transcript segment; the report described ongoing work and target completion dates.