Facilities committee backs Economides bus-drive repair recommendation; district outlines multiple campus projects and five-year plan

2959579 · April 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Facilities Committee recommended the board approve a contractor to repair the Johnny Economides bus drive, received updates on roofing, chillers, gym and lighting projects, and reviewed a draft five-year facilities plan and hurricane procedures annex with requested edits.

The ECISD Facilities Committee recommended the next board meeting include approval of a low bid to repair the bus drive at Johnny Economides and heard updates on district-wide projects and a draft five-year facilities plan and hurricane procedures annex.

Economides drive RFP and motion: Robert Gomez, ECISD director of facilities, presented RFP 25-55 for reconstruction of the Economides bus drive and said Real United Builders was the low, responsive bidder at $61,631 against a project budget of $200,000. After discussion, a committee member moved and a second was recorded to place the item on the next board agenda for approval; the committee chair instructed staff to proceed with bringing the recommendation to the full board.

Facilities project updates: Gomez and staff reported multiple active and planned projects: - Harwell campus chillers ordered; shipments expected mid-July and plans to provide portable-chiller hookups to avoid summer outages. - Roofing replacement projects at several elementary/middle sites and the transportation shop were advertised for spring bidding with construction anticipated in summer months. - Multiuse, metal buildings (60x90, ~5,400 sq ft) are in schematic design for each high school; the four-site program budget shown was $22,000,000, with $2,000,000 identified from a pending settlement for initial funding. - Truman elementary gym: final city inspection pending; district expects occupancy after tomorrow's inspection. - Edinburg North canopy lighting: contractor completed connections and staff reported final walk-through anticipated soon; district purchased impact-resistant LED fixtures and reported material and contractor savings relative to budgeted allowances.

Hurricane procedures handbook and five-year plan: Committee members reviewed a draft hurricane procedures annex and requested edits before approval. Ms. Vela and other members asked staff to provide a copy of the stated district/city statement of understanding, to correct outdated campus contact lists and to change wording to reflect that Red Cross leads shelter registration and district staff only assist. On the five-year facilities plan, staff presented a draft inventory of needs across 44 campuses; trustees asked to prioritize top three campus needs per school for budgeting and to involve principals in the prioritization process.

Board direction and next steps: The committee instructed staff to: - Advance the Economides RFP recommendation to the full board for approval at the next meeting, and prepare contract award documents. - Finalize and correct the hurricane annex language and contact pages for board review. - Continue refining the five-year plan and produce a prioritized, phased list for 2025-26 budget consideration.

Why this matters: The committee moved near-term construction and repair items that affect student safety and operations (bus drives, chillers, roofs and gym spaces) while seeking to clarify emergency procedures and prioritize multi-year capital needs for a district with multiple aging roofs, HVAC vulnerabilities and stormwater challenges.