SNHU Arena phase 1 work 41% complete; video wall delayed, staff optimistic about summer delivery
Summary
Committee on Baseball and Civic Center heard that phase 1 of capital improvements at SNHU Arena is about 41% complete, with about $1.4 million spent to date and the largest remaining expense—an imported video wall—delayed until roughly June.
The Committee on Baseball and Civic Center heard an update on phase 1 of capital improvements at SNHU Arena on an item presented during the committee meeting. Mister Becker, a staff member, told the committee the overall project is roughly 41% complete and that the largest outstanding cost is the arena's new video board, which has been delayed in transit.
The update matters because the remaining work affects upcoming events, commencements and operating equipment at the arena. Committee members asked whether construction would interfere with scheduled events and sought clarification on budgetary impacts and schedule risks.
Mister Becker said the original bond for phase 1 was $3,646,000. "We're at about 41% completion to date," he said, and reported spend to date of $1,400,000 with a balance to finish of just over $2,000,000. He told the committee that a large portion of the remaining cost—"in excess of $1,000,000"—is attributable to the central video wall. "The video components themselves are on a very slow boat from China. So we are hopeful they'll be here sometime in…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat