Summary

Staff briefed the council on a major waterline/cross-tow project, planned meter upgrades and the town’s capital constraints; the waterline procurement and timing remain subject to future funding decisions.

Town staff updated the Alta Town Council on several infrastructure projects on April 9, highlighting a multi-part waterline replacement and related utility work that the town expects to complete this summer and into the next fiscal year.

Why it matters: The waterline and meter upgrades affect the town’s long-term water reliability and interfacing infrastructure with U.S. Forest Service and ski-area projects; the procurement costs and funding choices also influence the town’s capital (CapEx) reserve and ability to fund other projects.

Staff said the immediate procurement covered materials and technical supervision and noted a contractor materials package and supervision contract of about $365,000; total project cost estimates discussed in the meeting ranged as high as $620,000. Staff also said the council earlier amended the budget to include $400,000 of waterline-related expense in the current fiscal year and that further borrowing or inter-fund loan decisions remain to be made.

The cross-tow utility project was described as a joint effort with the ski area to install new high-pressure ski lines, a town water main, and electric line restoration between Wildcat and Albion. Staff described a summer construction plan of staged trenching and pipe fusion across the alignment and said the schedule anticipates construction opening in May to allow work before winter.

Staff also reported ongoing meter upgrades: the town is switching to dual remote-reading water meters to improve billing and system management. Staff said most remaining meter installs are scheduled for the coming months.

Financial context: Staff presented a high-level projection that if the town purchased the Our Lady of the Snows building it would draw down CapEx reserves substantially, leaving balances under about $100,000 into 2026 and constraining the town’s ability to fund other larger projects such as a future replacement building. Staff mentioned a broader capital fund need—illustrated by a multi-million-dollar replacement projection for a future facility—and said large building projects would likely require debt or grants rather than pay-as-you-go CapEx transfers.

No final procurement vote for the full waterline project was taken at the meeting. The council did agree to reschedule the Facilities Master Plan presentation for May 14 to allow more time for staff work and public review.

Next steps: staff will continue procurement and contracting activity, finalize funding decisions (including possible inter-fund loan or general fund transfers), complete meter installs, and return to council with firm contract approvals and financing options.