Council OKs $1.5M amendment to T4 ground storage tank contract; funding to be reallocated from bonds
Summary
Kennedale council approved Amendment No. 1 to a storage tank contract, increasing the project to roughly $1.5 million to add turnkey work; council was told the increase is covered by ARPA/2023 bond funds and project timeline remains on track.
The Kennedale City Council unanimously approved Amendment No. 1 March 7 to expand the T4 ground-storage water tank contract into a turnkey package, raising the project cost from the previously quoted manufacturing-only price to about $1.5 million.
Staff said the original bid was for manufacturing only (approximately $996,000) and did not include piping, foundation work, testing and inspection. The single contractor that responded with a competitively lower total…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat