Council awards nearly $600,000 contract for six stormwater repair locations, approves 10% contingency
Summary
Council awarded a $599,471 construction contract to Southern Premier Contractors for six stormwater repair sites across the city and approved an additional 10% contingency for unforeseen underground issues, bringing the authorized total to $659,418.
Get email alerts on the Stormwater topic
No spam. Unsubscribe anytime.
The Tucker City Council voted to award a contract for repairs at six stormwater locations and approved a 10% contingency at its March 24 meeting.
Public works staff described six repair locations identified through service requests and an Atlas inventory and CCTV inspections: Mountain Shadow (1612), a site from DeKalb County records (6098), Rotherwood (2804), Woburn (identified by Atlas), Canadian Way (3458) and a wing wall at Lilburn‑Stone Mountain (1921). Staff described common failure modes — separated joints, holes in pipe walls, debris build‑up and sinkholes caused by soil migration — and said locations will be addressed with combinations of dig‑and‑replace, point grout repairs and cured‑in‑place lining. One site (Canadian Way) is a perennial, live stream-affected pipe requiring damming and dewatering during work.
Procurement: the city received eight bids and staff recommended awarding the base bid to Southern Premier Contractors. The base bid totaled $501,311; an alternate to repair the wing wall was $98,160, bringing the contract to $599,471. Council also approved a 10% contingency to cover unforeseen underground conditions such as buried construction debris or “bury pits”; with contingency the authorization is $659,418.
Why it matters: the work addresses active sinkholes and damaged drainage infrastructure that can undermine yards and, in some cases, roadways. Staff said neighbors were contacted and right‑of‑entry agreements or coordination are in place for all sites.
Vote: Council approved the contract award and added contingency; the motion passed unanimously (7–0).
Ending: Public works staff said on‑site inspectors will monitor the contractor daily and that council will be notified if any change orders exhaust the approved contingency.