Board rejects single Stonegate bid, will re‑solicit pipe replacement work

2941640 · April 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

An engineer's estimate for a failing corrugated metal pipe in Stonegate Subdivision was $83,765; the sole contractor bid was $136,900. The board voted to reject the single quote and re-solicit.

The Greenwood Stormwater Board voted April 9 to reject a single contractor quote for replacing a failing corrugated metal pipe in Stonegate Subdivision and to re‑advertise the work.

Staff said USI Engineers prepared design and an engineer’s estimate of $83,765 for the project. Chris Jones, director of stormwater management, said the lone bid received — from Warrior Excavating — totaled $136,900. Jones said the primary difference was the pipe cost: the engineer estimated $42,000 for the pipe while the contractor listed about $109,000 for pipe materials.

Jones asked the board to reject the quote and authorize staff to solicit additional bids. A motion to reject the single quote and re‑advertise was made, seconded and approved by voice vote.

Why it matters: the pipe is corrugated metal and failing, producing sinkholes in the area; board members said replacement in kind with reinforced concrete pipe (RCP) is planned, but the bid prices were well above the engineer’s estimate.

Next steps: staff will formally reject the single quote and advertise the project again, seeking additional competitive bids and returning with an updated recommendation.