Paulding County discusses asphalt surface-treatment award and approves extra engineering funds for Metromont Road

2940787 · April 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County staff recommended awarding a 2025 triple bituminous surface treatment contract for 8.695 miles to Northwest Georgia Paving and requested a supplemental engineering agreement with RK&K LLP to resume and extend design work on Metromont Road; funding sources cited were general funds and SPLOST.

Paulding County commissioners heard presentations on two transportation contracts: a recommended award of the 2025 asphalt bituminous surface treatment, Project No. 1, to Northwest Georgia Paving Inc. for $703,113.75, and a supplemental agreement with RK&K LLP to add $41,260 in engineering work on the Metromont Road improvements.

County Department of Transportation staff said the surface-treatment contract covers 8.695 miles, a triple bituminous surface treatment with prime coat and a box seal on 11 roads. DOT said the low bid of $703,113.75 was 17.5% lower than the county estimate and lower than a similar 2024 contract; funding for the surface-treatment project was identified as general-fund dollars.

Separately, staff described the Metromont Road design contract originally awarded to RK&K LLP on Sept. 28, 2021, for $129,268.56. DOT said work slowed because of staffing shortages and that resuming design requires additional scope for extended pay limits, right-of-way negotiation hours, revisions to Old Roper Road design, and traffic-control planning. The requested supplemental is $41,260, which DOT said brings the total engineering agreement to $170,528.56. DOT provided a tentative letting date of fall 2025 but noted multiple right-of-way parcels still must be acquired.

Why this matters: the projects affect safety and road surfaces across multiple commission posts. Commissioners asked staff for clarifications about per-mile costs, paving versus surface treatment choices, and constraints such as right-of-way limits that make full paving infeasible on some segments.

Details reported by staff: the surface-treatment contract covers a triple-surface aggregate-and-tar application intended to provide a harder sealed surface than basic crushed-millings treatments; the Metromont work will include widening a nonresidential segment to county nonresidential standards and intersection geometry improvements at Rosedale Drive and Ingram Road. DOT said funding for the RK&K supplemental will be provided by SPLOST (Special Purpose Local Option Sales Tax). The project schedule remains contingent on right-of-way acquisition.

No roll-call vote on the contract awards was recorded in the available transcript. DOT and finance staff recommended award of the asphalt surface-treatment contract to Northwest Georgia Paving Inc. and presented the RK&K supplemental for board authorization.

Ending: Staff said they will return with final agreements, right-of-way status updates and a refined letting timetable; commissioners did not state a formal roll-call vote on the surface-treatment award in the recorded segment.