Freetown Elementary entrance project proposed; town to bid concrete, adapt ADA ramps
Summary
A contractor and town representative outlined a plan to remove failing brick walls and trees at Freetown Elementary, replace walkways with roughly 12,700 square feet of concrete, make four wheelchair ramps ADA-compliant and seek bids this spring with construction after school ends.
A plan to reconstruct walkways and entrances at Freetown Elementary School was presented to the Freetown-Lakeville Regional School Committee, with town support and a bid timeline intended to put work in place over the summer.
Jim Noyce, representing the project team, told the committee that two low brick walls and several walkways adjacent to the main entrance are separating and have become trip hazards. The presentation called for removal of select…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat