West Chester staff outline sewer upgrades and pump purchases; phase 1 construction eyed for late summer
Summary
Public works staff reported permit and design timing for a major sewer upgrade (Maple Alley/Taylor Run/Goose Creek), upcoming bids and purchase orders for pumps and tanks, and an infiltration and inflow program; phase 1 construction was described as probable this year.
Get email alerts on the Sewer Upgrade Maple Alley topic
No spam. Unsubscribe anytime.
Public works staff briefed the committee on ongoing wastewater capital projects and near-term equipment purchases, including permits for a major sewer upgrade, procurement of sludge pumps, and installation of chemical storage tanks.
A staff speaker reported utility locating and video survey work for Maple Alley is complete and the design and DEP permit application are with the engineering firm Penone; staff said the goal is to submit permit materials by late May or early June, bid in July and award in August, with construction for Phase 1 targeted for completion between September and November. “We’re gonna design phase 1 and 2. We’re gonna bid phase 1 this year, complete it this year,” the staff speaker said.
Capital purchase orders discussed include a $29,000 primary sludge pump for Taylor Run (delivery 8–10 weeks) and two primary sludge pumps for Goose Creek with similar lead time. Staff also requested purchase orders for two 2,000-gallon chemical storage tanks ($59,000) and pumps/flow meters (approximately $23,820) for chemical feed systems.
Operational work updates: staff reported preventive maintenance at Goose Creek and Taylor Run, relining a storm sewer at Hoops Park, cleaning pump stations and starting a joint infiltration and inflow program with planned manhole inspections, video inspections and line metering.
Next steps: staff will continue design and permit submittal to DEP, complete procurements with anticipated 8–10 week deliveries for pumps, and proceed with bidding the Phase 1 construction package; specific contract award dates were not recorded in the transcript.