Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Facility Projects topic

No spam. Unsubscribe anytime.

Administration presents $15M-plus Boyertown Elementary HVAC and roof project; CHA outlines two-summer timeline

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Architect-engineer Jamie Lynch presented a proposed Boyertown Elementary renovation package — VRF HVAC, new roof, switchgear and generator replacement — with an all-in cost just over $15 million and a two-summer construction plan following 2025 design and public bidding.

The board heard a detailed presentation from CHA/Dewey project lead Jamie Lynch on a recommended mechanical and roofing project for Boyertown Elementary School that would replace aging unit ventilators with a variable-refrigerant-flow system, repair/replace the roof, and replace old switchgear and a noncompliant emergency generator.

Lynch said the team studied multiple HVAC options and recommends a VRF system with a modern building-management system to replace the pneumatic controls; he also proposed upgrading the electrical switchboard and relocating or upsizing the generator to move life-safety systems to a new exterior generator. Lynch described the proposed roof as EPDM with a bid alternate for TPO and said existing metal mansard roofs are currently in acceptable condition and were included in the bid only as an optional line item.

He presented a planning and construction timeline that completes design in 2025 and divides construction into two summer seasons (summer 2026 and summer 2027) to minimize disruption to occupied school operations. Total all-in project budget presented to the board was "just over $15,000,000," broken into hard costs, soft costs, roof, generator, big-box spaces and switchgear.

The consultant described typical project controls: competitive public bidding in accordance with Pennsylvania law; a resident project engineer (RPE) provided by the consultant to oversee contractors on-site; third-party testing and balancing (to be contracted directly by the district); and regular schedule updates, monthly payment review and retainage for contractor payments.

Board members asked about cold-weather backup capacity for heat pumps, contractor testing and balancing, the RPE role and independence (Lynch said the RPE and third-party testing firm would serve the district), site safety oversight, procurement lead times (switchgear and generators may require longer lead times) and payment/milestone processes. Lynch said manufacturer reps, third-party balancers, and resident engineers would document testing and hand over manuals and submittals to the district at project closeout.

Administration indicated the proposed professional-services agreement with CHA will be presented to the board for action at the April 22 legislative meeting.