Board advised to award $9.5 million bid for Lower Gulf Way sewer interceptor; action scheduled for regular meeting

2903940 · April 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Engineering staff recommended awarding the Lower Gulf Way interceptor alternate A to Coakley Company Inc. for $9,496,272; the project is part of an ADEQ consent administrative order and only alternate A was recommended at this time.

City engineering staff recommended awarding the Lower Gulf Way interceptor construction contract for Alternate A to Coakley Company Inc. for $9,496,272, Joey Stadler told the board at the April 15 agenda meeting.

Stadler said the work, designed by RJN, includes roughly 5,700 feet of 42-inch fiberglass-reinforced pipe and 14 manholes, beginning at the Gulf Basin Pump Station and following Gulf Creek. The award recommendation covers Alternate A only; four alternates were included in the bid form.

Stadler said the award recommendation is part of the city’s response to an ADEQ consent administrative order (LIS-22-077). He said Coakley was the only bidder and that RJN provided a certified bid tab and letter of recommendation dated Nov. 19, 2024; those documents are included in the packet.

The agenda meeting did not include a board vote; staff recommended the board consider the award at the upcoming formal meeting.