Hewitt updates utility and street projects; Commerce Park well on hold pending contractor schedule
Summary
City staff reported progress and timeline updates on Commerce Park well, Lift Station No. 4, plant work and upcoming street town hall for East Wall/Brierfield.
Hewitt — City staff on April 7 briefed the Hewitt City Council on ongoing utility and street projects, reporting a hold on the Commerce Park well work while awaiting contractor progress, and progress on plant and lift station tasks.
Miles Whitney, a city staff member who presented the written project report, said the Commerce Park well remains on hold pending the plant contractor’s return and that pump and motor installation is expected possibly in mid‑May. Whitney said pump testing will follow installation to secure potable approval from the Texas Commission on Environmental Quality (TCEQ).
On the plant portion of the Commerce Park project,…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat