Construction updates: Cherokee High transformer, Free Home finishings, Teasley driveway bid recommended
Summary
Capital outlay staff reported Cherokee High School remains on schedule and within budget as power and exterior lighting work proceeds; Free Home Elementary is nearly complete with furniture installation underway; staff recommended a contractor for Teasley Middle School driveway improvements.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Capital outlay staff updated the school board March 20 on several construction and maintenance projects across the district.
On the Cherokee High School replacement, Mr. Morse reported transformers from the utility have arrived and installation is under way, enabling systems testing on permanent power. He said data wiring installation and exterior light‑pole placement have begun and that the project remains on schedule and within budget.
Free Home Elementary is nearing completion: furniture installation and cafeteria work were scheduled to start in the coming weeks, with project closeout pending final punch‑list work and receipt of closeout documentation, Morse said. He thanked board members who attended a recent ribbon‑type community event at the school.
For Teasley Middle School, staff told the board the contractor recommendation for driveway improvements will come to the board during the evening business meeting for consideration. Mr. Morse said the contractor was recommended by the selection committee.
The presentation also listed summer maintenance plans across campuses, including flooring, painting, lighting, roofing and intercom work districtwide.