Committee approves base bid for 2025 chip seal program; fog‑seal deferred
Summary
The committee approved the low base bid of $135,378.98 for the 2025 chip seal program and decided not to accept the fog‑seal alternate this year, citing competing pavement maintenance needs and mixed field results for fog sealing.
Get email alerts on the Street Maintenance topic
No spam. Unsubscribe anytime.
The Public Works Committee voted to accept the low base bid of $135,378.98 from Carter (contractor name provided in bid documents) for the 2025 citywide chip‑seal program and to defer the fog‑seal alternate for the selected streets this year.
"Carter came in with the low bid for the base bid, for the amount of $135,378.98," Brad, Public Works staff, told the committee and recommended the base bid only. Staff said the committee's street and sidewalk maintenance priorities, plus pending mill‑and‑overlay contracts, made the base bid the better use of available funds this year.
Committee members discussed past test areas where fog sealing was used to coat chips and whether the extra cost (about a 25% increase when applied) produces measurable longevity benefits. "We did half of a project with fog seal and half without in order to determine its real effectiveness," one committee member said. Staff reported mixed results: some test sections held up better, while others showed normal chip loss in the first two years.
Staff said chip sealing generally yields a better cost‑benefit than microsurfacing for many local streets, and the committee approved proceeding with the base chip‑seal bid. The motion passed; staff will forward the award recommendation to City Council.