School committee approves $138,647.37 award and contract for concrete pad, storage building planned at East Providence High School

2885643 · January 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Committee awarded the East Providence High School concrete‑pad RFP to Duarte Corporation for $138,647.37 and approved the contract; staff described a 3‑bay 36x48 storage building to be sited on the pad and outlined an approximate eight‑week timeline subject to weather and city capital approval for the building purchase.

The School Committee approved the award of an RFP and the subsequent contract to construct a concrete pad at East Providence High School.

Procurement staff told the committee that six bids were received and, using the RFP rubric, recommended awarding the project to Duarte Corporation at $138,647.37. The memo to the committee listed scoring for bidders: Solitro Property Solutions (59), William H. Pepis (77), Marin Construction (50), Zayco (77), and Duarte Corporation (78).

Danny, a district facilities staff member, described the purpose: “The concrete pad is being put in place for a storage building that we desperately need. It'll be a ... 3 bay 36 by 48 building that'll sit on top of it. There also will be a concrete, pathway around the building.” He said the frame typically ships in 25 to 30 days and that, weather permitting, assembly and site restoration could finish in roughly eight weeks; that timetable would put completion in March, ahead of sports season start dates.

Funding and approvals: staff said the building purchase would come from capital projects funds and that city council approval is required to release those funds for ordering the building. A staff member said the Riverside savings referenced earlier were FEI grant money and that capital match clarifications would be provided as needed.

Votes and procedure: the committee approved the RFP award and then approved the contract at separate motions; both motions passed with voice votes (ayes). Committee members asked staff to provide follow‑up public information describing the pad and timeline.

Next steps: staff were asked to coordinate with the city to confirm capital project funding and to provide a clear procurement and installation schedule so the building can be ordered and installed in time for March occupancy, weather permitting.