Summary

County staff recommended a lease extension for a supplemental landfill flare skid to manage landfill gas while infrastructure upgrades are planned; staff estimated roughly two years of need and reported recent EGLE inspections found no violations.

St. Clair County staff told commissioners they expect to lease a supplemental flare skid to manage landfill gas while a longer‑term infrastructure upgrade is designed and constructed.

During the Environmental Public Works committee meeting, a commissioner asked how long the flare skid rental would be needed. County staff answered: “My best guess...probably about 2 years,” to provide additional vacuum to the gas system until a significant infrastructure upgrade is in place.

Staff said they are in an enforcement action with the Michigan Department of Environment, Great Lakes, and Energy (EGLE) but that recent inspections by the Air Quality and Materials Management divisions “didn't note any issues” and that no odor complaints to EGLE had been filed since early October of the prior year. The staff member characterized containment as adequate while long‑term fixes proceed.

A motion to send the flare skid lease extension with Perennial Energy to the full board was made, supported and carried on a voice vote; the committee did not record a roll‑call tally in the transcript.