Wiseburn USD, DaVinci to split Del Air baseball field costs; board issues notice to award
Summary
The Wiseburn Unified School District board voted 4-0 to approve a funding agreement with DaVinci Schools to build a baseball field near Del Air and to issue a notice of intent to award construction work, with the two parties sharing costs equally.
Get email alerts on the School Facilities topic
No spam. Unsubscribe anytime.
The Wiseburn Unified School District board voted 4-0 to approve a funding agreement with DaVinci Schools for construction of a baseball field located near Del Air and to issue a notice of intent to award so the project can move forward.
Board President Neil, presiding, made the motion to approve the funding agreement and asked staff to finalize the documents so the project could proceed. Board members voted unanimously to carry the motion.
District staff described the project cost as $1,277,079 and said the partners will split construction costs 50–50, at $638,539.64 each. Staff also said the agreement documents reflect an existing credit of $422,211 tied to rooftop mechanical equipment; after accounting for that credit, DaVinci Schools would transfer $216,328.64 to the district under the terms of the arrangement.
The motion authorized staff to issue a notice of intent to award and to finalize the funding agreement. Board materials indicated DaVinci will consider co-funding at an upcoming DaVinci meeting in April.
Board members framed the project as a long‑anticipated community asset that will provide local recreational opportunities for students and keep youth sports “at home.” The board did not set an opening date or construction timeline at the meeting.
Votes at the meeting on this item were recorded as 4 yes, 0 no. No individual board member votes were named in the transcript.
The board’s approval directs district staff to complete final contract paperwork and move the project into procurement and construction phases.