Pasco staff presents completion report for irrigation well upgrades; contractor final cost ~$521,000
Summary
Public Works staff said three irrigation wells were rehabilitated under a contract with Carpenter Drilling Company and recommended acceptance of the completed work; staff reported a final construction contract value of about $521,000, including change orders.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Director Sarah told the council that the well capacity upgrades project — aimed at rehabilitating three prioritized irrigation wells — is complete and recommended council acceptance of the contractor’s work. The project targeted the Northwest Commons well, Village at Pasco Heights well and the I‑182 well, work recommended by a 2018 study, Director Sarah said.
Staff described removing and right‑sizing pumps, rehabilitating well screens and performing required repairs. “That is a clean, clean well,” Director Sarah said in reference to before‑and‑after photos shown to the council. She said the original construction award to Carpenter Drilling Company was $517,000 and that change orders (including tax changes and additional pump repairs identified when pumps were pulled) brought the total construction contract to approximately $521,000.
Director Sarah said consultant recommendations include monitoring additional wells that might need rehabilitation in future phases. At the workshop staff presented the project completion and asked council to accept the work and authorize release of contract retainage; the transcript records the presentation but does not record a roll‑call vote on acceptance during the workshop.
No public comments or substantive questions followed the presentation; staff said retainage release and final project closeout would follow acceptance.