Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Utilities Wastewater topic

No spam. Unsubscribe anytime.

Council approves replacement of wastewater plant control system, budgeted at $411,000

2865698 · April 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council authorized a contract with Ralden Myers Inc. to replace the wastewater treatment plant SCADA system for not to exceed $403,441.50; staff said the project came in under the budgeted amount and the existing system dated from the late 1990s.

Oxford City Council adopted a resolution authorizing the city manager to enter into an agreement with Ralden Myers Inc. to replace the supervisory control and data acquisition (SCADA) computer control system at the wastewater treatment plant for a total cost not to exceed $403,441.50.

Staff told council the city had budgeted $411,000 for the project and that the existing automation system dates from the late 1990s and has reached the end of its useful life. Public-works staff said they received only one bid — consistent with expectations because of the specialized work — and recommended Ralden (Rod) Myers, citing the firm’s decades of work at the plant and at the water plant. “They’re extraordinarily qualified and have the knowledge of plant process control to work seamlessly with our staff,” staff said.

A councilor noted the importance of proactive maintenance for wastewater systems and thanked staff for the recommendation. The resolution was adopted by voice vote.