Bond update: high school steel rising; stadium work, portable packages and campus projects move toward summer
Summary
District staff updated trustees on progress across the 2025 bond program, reporting foundation pours, steel erections at the high school, stadium speaker installs, permitting steps for the athletic complex and schedules for Cambridge, Woodridge and Howard projects.
District project-control staff gave trustees a monthly bond update and schedule for work funded by the voter-approved bond program.
High school: Construction is underway on the high school north wing with steel erection visible and pans in place on the second and third floors; crews will pour concrete soon and continue utility runs and foundation work. Boiler replacement work has begun. Interior auditorium work (lighting, sound) is scheduled to start when school is out.
Stadium and athletic complex: East-side stadium foundation work is scheduled and contractor work to…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat